When you run a global ocean RFP, it never really “starts” the day you send out the file. The real work starts months earlier - in quiet conversations, messy spreadsheets, and the way you line up your own team.
I always tell people to picture the end date first. If you need contracts ready for an April 1 start, you do not want to be reacting at the last minute. You want a clean sequence - plan, invite, negotiate, and land agreements weeks before go-live.
The biggest mistake I see is letting “lowest rate” define success. Before a single bid comes back, get blunt with yourself and your leadership: are we solving for cost, service stability, flexibility, or capacity security? That answer should drive who you invite and how you score.
Then turn inward. A global RFP exposes misalignment fast - procurement, logistics, finance, and commercial teams all want different things. Name one owner, assign data and negotiation leads, and lock decision rules and scoring weights before bids arrive.
Finally, build a provider portfolio that can survive a tough year. Anchor your big, predictable lanes with carriers, and lean on NVOs/forwarders for volatile or complex trades - while avoiding too much volume with any one group. A well-run RFP is also where you build relationships: if you bring a true team, your providers will too. Those relationships are what save you when peak season gets ugly.
For junior pros: If your ocean spend is big enough to matter, push your leaders to treat the RFP like a serious project. Competitive does not mean cheapest - it means market-strong value from partners who will show up later.
Table 1. What to lock before bids arrive
|
Lock this down early |
Why it matters in ocean |
|
Define the win (cost vs.
stability vs. flexibility vs. capacity) |
You cannot score bids
fairly if success is fuzzy. |
|
Scope & assumptions
(lanes, terms, Incoterms, minimum requirements) |
Prevents “apples vs.
oranges” offers and surprise gaps. |
|
Total cost rules
(accessorials, free time, demurrage/detention) |
The “cheap” number often
is not the real cost later. |
|
Service expectations
(reliability, exception handling, visibility) |
Performance failures show
up as inventory, expedite, and customer pain. |
|
Provider strategy (carrier
vs. NVO/forwarder mix, allocations, backups) |
Builds resilience and
avoids over-concentration risk. |
|
Timeline & governance
(rounds, negotiation cadence, contract sign-off) |
Keeps you from awarding
late and scrambling at go-live. |
Tip: put these items in writing before Round 1. It saves weeks of arguing later.
Table 2. How WOWL helps clients run RFPs that stick
|
WOWL support |
What the client gets |
|
Align the team fast |
Clear roles, scoring, and
decision rules before bids land. |
|
Clean and package the bid |
Standard lanes, volumes,
and assumptions for true comparability. |
|
Shape the right provider
mix |
A portfolio built for both
steady lanes and disruption. |
|
Run the cadence and keep
it moving |
Round management, feedback
loops, and negotiations that stay on schedule. |
|
Make the award stick |
Allocations, KPIs, QBR
rhythm, and escalation paths post-award. |
Close: Run the RFP early, run it disciplined, and use it to build the partners you will depend on later. AndyG@WOWL.io